Horsham Hybrid Solar/BESS R1

Grid-Link led all grid connection activities for the Horsham Hybrid Renewable Park in Victoria, a 119MW solar and 100MW battery AC-coupled project, managing technical studies, regulatory approvals and coordination with AEMO and the NSP.

PROJECT SCOPE
  • Management of grid connection studies and the approval process through R1 and R2
  • Grid Compliance Monitoring Plan (GCMP)
  • Coordination with AEMO, the NSP and project stakeholders
  • HybridEMS development for three Power Plant Managers (PPM)
CHALLENGES
  • Managing grid connection for a hybrid generation and storage project with three PPMs
  • Coordinating multiple technical workstreams and stakeholder interfaces
  • Navigating complex performance and compliance requirements

OUTCOME

WE

CONNECT.

Grid-Link provided technical leadership across the connection process, coordinating studies, interfaces and approvals to reduce risk. An integrated Grid Lead role kept the connection pathway aligned with technical, regulatory and programme objectives.